Orchard Middle School
Facility Site ID:
771247
Cleanup Site ID:
447
Site Description
The school is located on former orchard property and was subject to historical pesticide applications. Soil samples taken in 2002 confirmed lead and arsenic at concentrations exceeding state cleanup levels.
After a Site Hazard Assessment, the site was ranked a “3” on the Hazardous Sites List. The Hazardous Sites List is a statewide list of contaminated properties. Sites can be ranked from a “1” to “5”. A rank of “1” is the highest level of environmental concern compared to other sites on the List, and a rank of “5” is the lowest.
After a Site Hazard Assessment, the site was ranked a “3” on the Hazardous Sites List. The Hazardous Sites List is a statewide list of contaminated properties. Sites can be ranked from a “1” to “5”. A rank of “1” is the highest level of environmental concern compared to other sites on the List, and a rank of “5” is the lowest.
Cleanup Activities
During the summer of 2008, Ecology conducted a cleanup and placed all contaminated soils under a geotextile fabric barrier. Then, six inches of clean topsoil were placed on top on the barrier fabric. This cleanup method, referred to as capping, is cost-effective and prevents human exposure to contaminated soil.
Following cleanup, an environmental covenant was recorded for the property with the Chelan County Assessor. The purpose of the environmental covenant is to provide a permanent legal record of the contamination that remains on the property, and to prevent activities at the site that might disturb or damage the soil cap.
Following cleanup, an environmental covenant was recorded for the property with the Chelan County Assessor. The purpose of the environmental covenant is to provide a permanent legal record of the contamination that remains on the property, and to prevent activities at the site that might disturb or damage the soil cap.
Cleanup Complete
Based on the cleanup completed and the recording of the environmental covenant, Ecology has determined the site does not pose a threat to human health or the environment. Ecology issued a no further action determination in April 2011. The site has been removed from the Hazardous Sites List.
Site use restrictions called institutional controls are in effect
Institutional controls can be fences, signs, or restrictions on how the property is used. For instance, an institutional control may prohibit installing drinking water wells or disturbing a protective cap that isolates contamination. These restrictions keep the contamination contained and keep people from being exposed to the contamination. The controls are usually listed in environmental covenants recorded with the county.
Periodic reviews are required when institutional controls are required at a site. Ecology conducts reviews to make sure the controls remain effective and the cleanup still protects human health and the environment. We conduct periodic reviews about every five years.
Institutional Controls 1
Environmental Covenant
County Recording #:
2319623
County Recording Date:
2/24/2010
Restrictions/Requirements
- Ongoing Maintenance of Remedy
- Prohibit Soil Disturbance
- Restrict Access
Restricted Media
- Soil
Documents 15
Legal 2
Document Title | Document Date | Document Type |
Orchard Middle School - No Further Action letter | 4/25/2011 | NFA Letter – non-VCP |
Orchard Middle School - Covenant 2319623 | 2/24/2010 | Environmental Covenant; Alternative Mechanism |
Public Information 3
Document Title | Document Date | Document Type |
Orchard Middle School and Sunnyslope Elementary School - delisting fact sheet | 1/1/2010 | Fact Sheet\Public Notices |
Orchard Middle School and Sunnyslope Elementary School - Interim Action Plan SEPA 2008 fact sheet | 4/30/2008 | Fact Sheet\Public Notices |
Orchard Middle School and Sunnyslope Elementary School - Interim Action Plan SEPA 2007 fact sheet | 3/1/2007 | Fact Sheet\Public Notices |
State Environmental Policy Act 4
Document Title | Document Date | Document Type |
Orchard Middle School and Sunnyslope Elementary School - SEPA DNS 2008 | 4/30/2008 | SEPA Documents |
Orchard Middle School and Sunnyslope Elementary School - SEPA checklist 2008 | 4/22/2008 | SEPA Documents |
Sunnyslope ES & Orchard MS SEPA DNS 2007 | 3/22/2007 | SEPA Documents |
Orchard Middle School and Sunnyslope Elementary School - SEPA checklist 2007 | 3/19/2007 | SEPA Documents |
Technical Reports 6
Document Title | Document Date | Document Type |
Orchard Middle School - Notice of Periodic Review | 10/22/2024 | Site Specific Administrative Document - other (Administrative correspondence) |
Orchard Middle School - Periodic Review July 2022 | 7/11/2022 | Periodic Review (5 Year) |
Orchard Middle School - Final Interim Action Report | 11/20/2009 | Interim Action Documents |
Orchard Middle School and Sunnyslope Elementary School - Interim Remedial Action Plan 2008 | 4/1/2008 | Interim Action Documents |
Orchard Middle School and Sunnyslope Elementary School - Interim Remedial Action Plan 2007 | 3/19/2007 | Interim Action Documents |
Orchard Middle School - Site Hazard Assessment | 2/1/2006 | Site Hazard Assessment Report |
There may be more documents related to this site. To obtain documents not available electronically, you will need to make a public records request.
Places to see print documents
-
Central Regional Office1250 W Alder StUnion Gap, 98903-0009Please schedule an appointment to view print documents at this location.
Contaminants 1
Contaminant Type | Soil |
Groundwater |
Surface Water |
Air |
Sediment |
Bedrock |
---|---|---|---|---|---|---|
Metals - Metals Priority Pollutants | RA |
- S
- Suspected
- C
- Confirmed Above Cleanup Levels
- B
- Below Cleanup Levels
- RA
- Remediated-Above
- RB
- Remediated-Below
- R
- Remediated
This contaminant list was based on our best information at the time it was entered. It may not reflect current conditions at the site.
Public Comment Period
Comments will be accepted October 30, 2024 through November 29, 2024.
You may submit your comments online or by mail to Frank Winslow, Periodic Reviewer, at Ecology's Central Regional Office.
We complete a periodic review about every five years cleanup construction is complete at a site when institutional controls are part of the cleanup. The purpose of the review is to make sure the controls remain effective and the cleanup still protects human health and the environment.
We will review comments received during the comment period and make recommendations for suggested changes. The periodic review will become final if no significant changes are made. An additional public comment period will be held if significant changes are made.