Kaiser Aluminum & Chemical Corporation

Facility Site ID: 53481373 Cleanup Site ID: 7093

 

Site History

Kaiser Aluminum & Chemical Corporation’s Trentwood facility (Kaiser Trentwood) produces aluminum sheet, plate, and coil for aerospace and general engineering applications.

The federal government built the facility during World War II, and it first produced aluminum sheet in 1943. After the war ended, the facility was sold to private interests and has processed aluminum since.

Materials used in past aluminum production included polychlorinated biphenyl (PCB) oil, petroleum fuels, solvents, and chromium. Wastes generated as a result of past or present operations are wastewaters, chrome sludge, paint and solvent wastes, and black dross.

Cleanup

Several releases of contamination have occurred at the Kaiser Trentwood site due to historical operations. Kaiser investigated the contamination and completed interim cleanup actions to address groundwater and soil contamination coming from these releases. Full-scale testing of a treatment system that uses ultraviolet light and an advanced oxidation process to destroy PCBs in groundwater is ongoing. The results will inform the final cleanup plan.

Remedial investigation and feasibility study

In 2010, Kaiser investigated nine areas at the site to better understand contaminants in soil and groundwater, where they were located, and how much was present at the site.

Since completing the investigations, Ecology requested more information about the west discharge ravine area, where wastewater was formerly discharged to the Spokane River. This investigation more clearly defined possible sources of PCB contamination in groundwater.

The feasibility study evaluated information from the investigations and outlined cleanup options for contaminants in soil and groundwater at the site.

  • Please visit the Technical Reports section of the site documents to view the multi-volume remedial investigation and feasibility study that was completed in 2012.
Interim cleanup actions and groundwater tests leading to final cleanup plan

Kaiser has completed many interim cleanup actions, including removing petroleum on groundwater and excavating or capping contaminated soil. PCB contamination in groundwater is the primary remaining issue.

To find the most effective method, Kaiser pilot tested the following ways to remove PCBs from groundwater from 2013–2022:

  1. Walnut-shell filtration
  2. Algae filtration
  3. Solvent extraction with zero-valent metal treatment
  4. Ultraviolet light/advanced oxidation (adding hydrogen peroxide, basically) process, or UV/AOP

The first three methods only captured PCBs and created a new waste stream to be managed and disposed, along with other technical issues, while UV/AOP was highly efficient at destroying PCBs. In 2022, Ecology and Kaiser agreed to move forward with full-scale implementation of UV/AOP. You can learn more in the Interim Action Completion Report.

In early 2024, Kaiser will begin operating a full-scale UV/AOP system. Ecology’s legal agreement with Kaiser requires the full-scale system to extract contaminated groundwater at rates that protect the Spokane River. It also requires they improve and expand the system, as necessary. Kaiser will operate the full-scale system for several years. Ecology will write the draft cleanup action plan after we assess the results of the testing and the system’s ability to meet state standards. The draft plan will be available for public review before becoming final.

Legal 4
Document Title Document Date Document Type
Amendment No. 2: Agreed Order 2692 for Kaiser Trentwood site 2/3/2020 Agreed Order Amendment
Kaiser Trentwood Agreed Order for FFS July 2012 7/12/2012 Agreed Order
Kaiser Aluminum AO Remedial Action 6/6/2005 Agreed Order
Kaiser Trentwood Consent Decree 2/6/2003 Consent Decree
Public Information 14
Document Title Document Date Document Type
Response to Comments: Draft Agreed Order Amendment for Kaiser Trentwood Facility 4/29/2020 Responsiveness Summary
Kaiser Trentwood Cleanup Presentation: Interim Action for Groundwater (public meeting 4/8/20) 4/8/2020 Multimedia
Comment period extension for draft amended legal agreement and State Environmental Policy Act documents to test groundwater treatment options: Kaiser Trentwood 3/18/2020 Fact Sheet\Public Notices
Public invited to comment on amended legal agreement & SEPA docs: Kaiser Trentwood 2/24/2020 Fact Sheet\Public Notices
Kaiser Trentwood Hazardous Waste Closure Plan 9/4/2013 Fact Sheet\Public Notices
Responsiveness Summary AO RI Addendum and FFS 9-2012 9/26/2012 Responsiveness Summary
Kaiser Trentwood Fact Sheet AO for FFS, RI Addendum, SEPA 8/20/2012 Fact Sheet\Public Notices
Responsiveness Summary for the Remedial Investigation and Feasibility Study 3/29/2012 Responsiveness Summary
Fact Sheet Remedial Investigation Feasibility Study Reports Chart Figure 3 1/5/2012 Fact Sheet\Public Notices
Fact Sheet Remedial Investigation Feasibility Study Reports Figure 2 1/5/2012 Fact Sheet\Public Notices
Fact Sheet Remedial Investigation Feasibility Study Reports 1/5/2012 Fact Sheet\Public Notices
Kaiser Aluminum Fact Sheet Fabricated Products Trentwood Site Interim Actions 5/1/2007 Fact Sheet\Public Notices
Kaiser Trentwood Site - Agreed Order Response to Comments 8/17/2005 Responsiveness Summary
Kaiser Aluminum Fact Sheet AO for RI/FS 6/1/2005 Fact Sheet\Public Notices
State Environmental Policy Act 6
Technical Reports 24
Document Title Document Date Document Type
Phase 1 Interim Action Completion Report: Kaiser Trentwood 1/23/2023 Interim Action Documents
Kaiser Trentwood Focused Feasibility Study WDR 2012 7/19/2012 Feasibility Study
403 Focused Feasibility Study West Discharge Ravine Kaiser Trentwood Site 2012 7/19/2012 Feasibility Study
401 Agreed Order for Interim Actions and West Discharge Ravine Kaiser Trentwood Site 2012 7/19/2012 Interim Action Documents
FINAL Remedial Investigation Report GROUNDWATER Vol II Appendix F Tables Kaiser Trentwood 2012 5/31/2012 Remedial Investigation Report
FINAL Remedial Investigation Report GROUNDWATER Vol II Appendix F Kaiser Trentwood 2012 5/31/2012 Remedial Investigation Report
014 FINAL Remedial Investigation Report GROUNDWATER Vol I Appendix Plate 2 Kaiser Trentwood 5/31/2012 Remedial Investigation Report
307 FINAL Remedial Investigation Report GROUNDWATER Vol I Appendix Plate 1 Kaiser Trentwood 5/31/2012 Remedial Investigation Report
306 FINAL Remedial Investigation Report GROUNDWATER Vol I Appendix E Kaiser Trentwood 5/31/2012 Remedial Investigation Report
305 FINAL Remedial Investigation Report GROUNDWATER Vol I Appendix D Kaiser Trentwood Site 5/31/2012 Remedial Investigation Report
304 FINAL Remedial Investigation Report GROUNDWATER Vol I Appendix C PCB Congener Transport Model 5/31/2012 Remedial Investigation Report
303 FINAL Remedial Investigation Report GROUNDWATER Vol. I Appendix B Table 5/31/2012 Remedial Investigation Report
302 FINAL Remedial Investigation Report GROUNDWATER Vol I Appendix A Well Logs 2012 5/31/2012 Remedial Investigation Work Plan
301 FINAL Remedial Investigation Report GROUNDWATER Vol I Kaiser Trentwood May 2012 5/31/2012 Remedial Investigation Report
202 FINAL Remedial Investigation Report SOIL Vol II - Kaiser Trentwood May 2012 5/1/2012 Remedial Investigation Report
201 FINAL Remedial Investigation Report SOIL Vol I - Kaiser Trentwood May 2012 5/1/2012 Remedial Investigation Report
002 FINAL Feasibility Study Vol II - Kaiser Trentwood May 2012 5/1/2012 Feasibility Study
001 FINAL Feasibility Study Vol. I - Kaiser Trentwood May 2012 5/1/2012 Feasibility Study
003 FINAL Feasibility Study Technical Memorandum Final - Kaiser Trentwood May 2012 5/1/2012 Feasibility Study
004 FINAL Human Health Risk Assessment Kaiser Trentwood May 2012 5/1/2012 Human Health and/or Eco Risk Assessment
Kaiser Agreed Order RI Addendum 2012 4/3/2012 Remedial Investigation Report
402 Remedial Investigation Addendum West Discharge Ravine Kaiser Trentwood Site 2012 4/3/2012 Remedial Investigation Report
Kaiser Aluminum Draft West Discharge Ravine Interim Action Work Plan 5/21/2007 Interim Action Documents
Kaiser Trentwood Periodic Review 5/1/2007 Periodic Review (5 Year)
There may be more documents related to this site. To obtain documents not available electronically, you will need to make a public records request.

Places to see print documents

  • Eastern Regional Office
    N 4601 Monroe St
    Spokane, 99205-1265
    Please schedule an appointment to view print documents at this location.
  • Spokane Valley Public Library
    12004 East Main
    Spokane Valley, 99216
    This location may only have print documents available during open comment periods.

Contaminants 5

Contaminant Type
Soil
Groundwater
Surface Water
Air
Sediment
Bedrock
Metals - Metals Priority Pollutants C S
Halogenated Organics - Polychlorinated biPhenyls (PCB) C C S
Non-Halogenated Organics - Petroleum Products-Unspecified C S
Other Contaminant - Conventional Contaminants, Inorganic C C
Non-Halogenated Organics - Petroleum-Other C
S
Suspected
C
Confirmed Above Cleanup Levels
B
Below Cleanup Levels
RA
Remediated-Above
RB
Remediated-Below
R
Remediated
This contaminant list was based on our best information at the time it was entered. It may not reflect current conditions at the site.