Facility Site ID: 2893 Cleanup Site ID: 102

Current Status

Laurel Station cleanup site location
Laurel Station cleanup site location

Last Updated, September 2018

Compliance monitoring is ongoing. Additional cleanup will be performed if necessary.
 
Petroleum-contaminated soil occurred in three localized areas (see also map below):
1.    Pump Station Area
2.    Tank 180
3.    Material Storage Area
 
Remedial actions completed in July 2015 (cleanup system operations ongoing):
 
Pump Station Area:

  • Direct removal and disposal:  Excavated accessible soil and sent for off-site disposal.
  • Subsurface process:  Where inaccessible by direct excavation, contaminated soil and groundwater are cleaned up below ground with a dual-phase extraction (DPE) process.  This consists of a series of dedicated wells that remove both liquid and vapor phase contamination.  DPE began in July 2015 and has operated continuously since.
  • Site Use Controls: Less highly contaminated soil that is contained by pavement or buildings will be left in place with legal site use controls dictating it to be cleaned up when structures are decommissioned or maintenance exposes contaminated soil, at which time it will be excavated and sent for off-site disposal. 

 Tank 180 Area:

  • Site Use Controls: Contaminated soil beneath Tank 180 will remain contained with legal site use controls dictating it to be cleaned up when the structure is decommissioned or maintenance exposes contaminated soil, at which time it will be excavated and sent for off-site disposal.

 Material Storage Area:

  • Direct Removal and disposal:  Excavated soil and sent for off-site disposal.
Laurel Station cleanup site map
Laurel Station cleanup site map

General Cleanup Process

The Model Toxics Control Act (MTCA; Chapter 70.105D RCW is Washington’s environmental cleanup law). It provides requirements for contaminated site cleanup and sets standards that protect human health and the environment. Ecology enacts the MTCA and oversees cleanups. The MTCA site cleanup process is completed in steps (see graphic below) over a variable timeline.

Site Timeline

  • June 2014:  Remedial Investigation/Feasibility Study (RI/FS) Report completed and Cleanup Action Plan (CAP) included in legal agreement (Consent Decree)
  • September 2014:  Cleanup design completed.
  • January 2015:  Compliance Monitoring Plan completed.
  • July 2015:  Remedial cleanup actions were completed.  Subsurface dual-phase extraction (DPE) process begins operation.
  • Ongoing:  Subsurface removal system continues contaminant extraction.  Periodic monitoring is conducted to assess effectiveness of the cleanup.  Additional cleanup will be performed if necessary.

Public Participation

Current Laurel Station cleanup site Public Participation Plan

This plan includes information for the public regarding opportunities to get involved in the Site cleanup process. The outreach activities and mechanisms presented reflect Ecology’s current plans for keeping the public informed and for receiving information and comments from the public. 

Site Information

Laurel Station aerial view; East Smith Road is located in image upper left
Laurel Station aerial view; East Smith Road is located in image upper left
Site History
Laurel Station was constructed in 1956, and is used to transport crude oil via pipeline from Edmonton, Alberta, Canada, to refineries at Ferndale and Anacortes, Washington.  The facility currently consists of 20-inch and 16-inch pipelines, a pump station, associated storage tanks, and support buildings.

Contamination
Petroleum contamination at the Site resulted from historic release of crude oil and natural gas condensate between 1971 and 2000.  Most of the releases had been cleaned up before the remedial action have already been cleaned up.  This cleanup addresses the areas that remain impacted by historic releases.
Legal 10
Map 1
Document Title Document Date Document Type
Laurel Station Site Map 4/14/2014 Map
Public Information 2
Document Title Document Date Document Type
Laurel Station - Fact Sheet (April 2014) 4/18/2014 Fact Sheet\Public Notices
Laurel Station - Public Participation Plan 4/18/2014 Public Participation Plan
Technical Reports 24
Document Title Document Date Document Type
AECOM Progress Report – July 1, 2021 to March 31, 2023 5/4/2023 Progress Report
AECOM Progress Report – July 1, 2021 to March 31, 2023 5/4/2023 Progress Report
AECOM Progress Report – January 1 to June 30, 2021 8/19/2021 Progress Report
AECOM Progress Report – July 1, 2020 to December 31, 2020 1/22/2021 Progress Report
AECOM Progress Report – July 1 to December 31, 2019 1/21/2020 Progress Report
URS Progress Report – December 1, 2018 to December 31, 2018 2/21/2019 Progress Report
Laurel Station Progress Report - May 2018 5/4/2018 Progress Report
URS Progress Report – October 1 to December 31, 2017 1/19/2018 Progress Report
URS Progress Report – April 1 to August 31, 2016 9/8/2016 Progress Report
Laurel Station DPE O&M Manual 2/5/2016 Operation and Maintenance Plan
URS Progress Report – October 1 to December 31, 2015 1/21/2016 Progress Report
Compliance Monitoring Plan 1/16/2015 Engineering Design Report
URS Progress Report – November 1 to 30, 2014 12/19/2014 Progress Report
Laurel Station EDR Sep 2014 Vol 2 9/9/2014 Engineering Design Report
Laurel Station EDR Sep 2014 Vol 1 9/9/2014 Engineering Design Report
Additional Investigation - Pump Station Area 7/24/2014 Scope Of Work
Final Remedial Investigation/Feasibility Study, Laurel Station - database 6/2/2014 Remedial Investigation / Feasibility Study
Final Remedial Investigation/Feasibility Study Report, Laurel Station 6/2/2014 Remedial Investigation / Feasibility Study
Final Dual Phase Extraction and Bioventing Pilot Test Work Plan, Laurel Station 11/30/2011 Remedial Investigation Work Plan
Proposed Additional Data Gap Investigation Sampling and Pilot Testing Activities, Laurel Station 5/23/2011 Remedial Investigation Work Plan
Proposed Additional Data Gap Investigation Sampling Activities, Laurel Station 1/20/2011 Remedial Investigation Work Plan
Proposed Additional Data Gap Investigation Sampling Activities, Laurel Station 8/5/2010 Remedial Investigation Work Plan
Final Supplemental Remedial Investigation/Feasibility Study Work Plan, Laurel Station 5/28/2010 Remedial Investigation Work Plan
Remedial Invvestigation/Feasibility Study Work Plan, Trans mountain Oil Pipe Line, Corp, Laurel Station 9/30/1992 Remedial Investigation Work Plan
There may be more documents related to this site. To obtain documents not available electronically, you will need to make a public records request.

Places to see print documents

  • Northwest Regional Office
    15700 Dayton Ave N
    Shoreline, 98133
    Please schedule an appointment to view print documents at this location.
  • Ecology Bellingham Field Office
    913 Squalicum Way, Unit 101
    Bellingham, 98225
    This location may only have print documents available during open comment periods.
  • Bellingham Public Library
    210 Central Ave
    Bellingham, 98225
    This location may only have print documents available during open comment periods.

Contaminants 1

Contaminant Type
Soil
Groundwater
Surface Water
Air
Sediment
Bedrock
Non-Halogenated Organics - Petroleum Products-Unspecified C S
S
Suspected
C
Confirmed Above Cleanup Levels
B
Below Cleanup Levels
RA
Remediated-Above
RB
Remediated-Below
R
Remediated
This contaminant list was based on our best information at the time it was entered. It may not reflect current conditions at the site.