Background

The North Marina Ameron/Hulbert site is part of the Port of Everett’s Waterfront Place Redevelopment. It is generally located between 11th and 13th streets, west of West Marine View Drive in Everett, Snohomish County, WA. Primary uses of the site since the late 1800s have included shingle and saw milling, marine support services, and concrete pole and piling manufacturing. The William Hulbert Mill Company (Hulbert) owned most of the site from 1923 to 1991 and conducted mill operations at the Site until approximately 1960. In approximately 1972, Hulbert leased a large portion of the Site to Centrecon, a concrete pole manufacturing company. Utility Vault Company (UVC; now Oldcastle Precast Inc) purchased Centrecon in 1978. In 1988, Ameron International (Ameron) entered into an asset purchase agreement with UVC, whereby it purchased most of the assets, properties and business of UVC's Centrecon division. The Port of Everett (Port) purchased the property from Hulbert in 1991 and used a portion of the property to stockpile soil from other Port properties. Under a lease, Ameron currently manufactures decorative concrete poles at the site.

The Port completed extensive investigation and partial cleanup of the site under Ecology’s voluntary cleanup program. An investigation to fully characterize contamination at the site has been completed. Interim actions removed approximately 22,000 cubic yards of contaminated soil and cleaned out and repaired stormwater lines.

Status

Ecology and the PLPs entered into an Agreed Order for site cleanup on June 3, 2009. The Agreed Order requires the PLPs to develop an Interim Action Cleanup Report, a Remedial Investigation and Feasibility Study (RI/FS) work plan to evaluate the nature and extent of Site contamination, an RI/FS Report, and a Draft Cleanup Action Plan to describe the proposed cleanup action and outline cleanup requirements for the site.
Key milestones are summarized below.

  • The Interim Action Cleanup Report, which details investigation and cleanup work conducted prior to the Agreed Order, was finalized on April 8, 2010.
  • The RI/FS work plan was developed and Ecology approved it on November 17, 2010.
  • Field RI – Initial RI field activities commenced in late November 2010 with the collection of soil and groundwater samples. Sediment samples were collected from the 12th Street Marina in December 2010. Supplemental RI sampling (collection of soil and groundwater samples) was conducted in January 2011 to investigate conditions associated with the recently de-constructed Collins Building (removed in November 2010). Two areas with petroleum contamination that are exposed to the elements were identified.
  • An RI Data Report detailing the results of the initial investigation was received in
    June 2011.  The RI Data Report was used to identify additional data needs to define the full nature and extent of contamination at the site.
  • Emergency Action (Removal of Petroleum Contaminated Soil) - Ecology instructed the PLPs to remove the soil contaminated with petroleum within the footprint of the de-constructed Collins Building to reduce the threat of contaminants migrating and to prevent human direct contact. The emergency action was conducted in August 2011. Approximately 79 cubic yards of contaminated soil were removed and transported off-site for treatment and disposal. The technical report for this action was appended to the DCAP.
  • Additional RI sampling, which consisted of soil, groundwater, surface water, stormwater solids, and process waste sampling, was conducted in October and December 2011. Further soil sampling was conducted in May 2013 to evaluate the nature and extent of soil contamination in two areas of the site.
  • Emergency Action (Stormwater System Repair) – An emergency action to decommission and replace a portion of an existing stormwater pipe that discharges to the 12th Street Yacht Basin was completed in December 2013. Approximately 13 tons of accumulated sediments with elevated concentrations of several hazardous substances were removed as part of the emergency action. The technical report for this action is appended to the DCAP.
  • Emergency Action (Removal of Contaminated Soil and Stormwater System Repair) – In 2014, an additional emergency action was taken to remove about 3,200 tons of soil contaminated or potentially contaminated with metals and replace a damaged section of storm drain. The technical report for this action is appended to the DCAP.
  • A final RI/FS Report was submitted to Ecology in April 2014 after undergoing public review. The RI/FS Report describes contamination and possible cleanup action alternative at the site.
  • A draft Consent Decree (CD) was prepared in September 2014. The CD is a formal legal document between Ecology and the PLPs that requires the PLPs to carry out specifically identified cleanup actions. The draft CD was available for public comment from October 10 to November 8, 2014.
  • A draft Cleanup Action Plan (DCAP) was prepared in September 2014. The DCAP describes the proposed cleanup action for the site and outlines requirements for the cleanup, including specifically required cleanup actions. The DCAP was available for public comment from October 10 to November 8, 2014.
  • A draft State Environmental Policy Act (SEPA) Determination of Non-Significance (DNS) and Checklist was prepared in September 2014. The SEPA DNS identifies potential environmental impacts of the project on the surrounding environment. The document includes Ecology's determination that site cleanup will not have a probable significant adverse impact on the environment. The draft SEPA DNS was available for public comment from October 10 to November 8, 2014.
  • A draft Public Participation Plan (PPP) was prepared in September 2014. The PPP is an update to prior PPPs for this site and explains how the public can provide input on the cleanup. The draft PPP was available for public comment from October 10 to November 8, 2014.

Final cleanup is anticipated for 2017.

Legal 4
Public Information 4
Document Title Document Date Document Type
North Marina Ameron Hulbert - Public Participation Plan (November 2014) 11/21/2014 Public Participation Plan
North Marina Ameron Hulbert - Fact Sheet - October 2014 CD/DCAP 10/1/2014 Fact Sheet\Public Notices
North Marina Ameron Hulbert - Fact Sheet - March 2014 RI/FS 3/6/2014 Fact Sheet\Public Notices
North Marina Ameron Hulbert - Fact Sheet - April 2009 Agreed Order 4/13/2009 Fact Sheet\Public Notices
State Environmental Policy Act 2
Document Title Document Date Document Type
North Marina Ameron Hulbert - Notice of Determination of Non-Significance (DNS) 10/1/2014 SEPA Documents
North Marina Ameron Hulbert - SEPA Checklist 9/12/2014 SEPA Documents
Technical Reports 26
Document Title Document Date Document Type
North Marina Ameron Hulbert - Soil and Groundwater Management Plan 2/24/2017 Site Specific Technical Document - other
North Marina Ameron Hulbert - Cleanup Action Plan 11/21/2014 Cleanup Action Plan
North Marina Ameron Hulbert - Construction Completion of Emergency Action for Areas G-1B and G-3 8/28/2014 Interim Action Documents
North Marina Ameron Hulbert - Construction Documentation Stormwater Trunk Line Cleanout and Repair Emergency Action 7/24/2014 Interim Action Documents
North Marina Ameron Hulbert - Post-RI Supplemental Soil Characterization Plan 6/4/2014 Sampling and Analysis Plan
North Marina Ameron Hulbert - RI/FS Draft Report - Appendices A to I 4/30/2014 Remedial Investigation / Feasibility Study
North Marina Ameron Hulbert - Final Report - Main Text, Tables, and Figures 4/30/2014 Remedial Investigation / Feasibility Study
North Marina Ameron Hulbert - Addendum No. 1 - Emergency Action Work Plan for Areas G-1B and G-3 Supplemental Soil Investigation - Area G-1B Emergency Action SD8 Area 4/23/2014 Interim Action Documents
North Marina Ameron Hulbert - Emergency Action Work Plan. For Areas G-1B and G-3 2/6/2014 Interim Action Documents
North Marina Ameron Hulbert - Emergency Action Amendment. Stormwater Trunk Line Cleanout and Repair 11/15/2013 Interim Action Documents
North Marina Ameron Hulbert - Addendum #3 - RI/FS Work Plan 5/24/2013 Remedial Investigation Work Plan
North Marina Ameron Hulbert - Emergency Action Cleanup Plan. Stormwater Trunk Line Cleanout and Repair 9/19/2012 Interim Action Documents
North Marina Ameron Hulbert - RI/FS Work Plan Addendum 2 12/7/2011 Remedial Investigation Work Plan
North Marina Ameron Hulbert - Emergency Action Cleanup Craftsman District Boatyard Expansion Area 11/7/2011 Interim Action Documents
North Marina Ameron Hulbert - RI Data Report 6/20/2011 Remedial Investigation Report
North Marina Ameron Hulbert - Site Emergency Action Cleanup Plan 5/3/2011 Interim Action Documents
North Marina Ameron Hulbert - RI/FS Work Plan Addendum 1 1/18/2011 Remedial Investigation Work Plan
North Marina Ameron Hulbert - Final RI/FS Work Plan - Appendices A to G 11/17/2010 Remedial Investigation Work Plan
North Marina Ameron Hulbert - Final RI/FS Work Plan - Main Text, Tables, and Figures 11/17/2010 Remedial Investigation Work Plan
North Marina Ameron Hulbert - Historical Site Development Analysis 5/11/2010 Remedial Investigation Work Plan
North Marina Ameron Hulbert - Final Interim Action Report 4/7/2010 Interim Action Documents
North Marina Ameron Hulbert - Site Hazard Assessment 7/22/2008 Site Hazard Assessment Report
North Marina Ameron Hulbert - Ecology Review Draft Data Gaps Investigation 5/13/2005 Site Specific Technical Document - other
North Marina Ameron Hulbert - Ecology Review Draft Phase II Environmental Site Assessment 4/13/2004 Site Specific Technical Document - other
North Marina Ameron Hulbert - Phase I Environmental Site Assessment 11/28/2001 Site Specific Technical Document - other
North Marina Ameron Hulbert - Phase I ESA and Phase I Audit Business on 30 Acres Northwest Corner of 13th Street and Marine View Drive 5/29/1991 Site Specific Technical Document - other
There may be more documents related to this site. To obtain documents not available electronically, you will need to make a public records request.

Places to see print documents

  • Headquarters
    300 Desmond Dr SE
    Lacey, 98503
    Please schedule an appointment to view print documents at this location.

Contaminants 10

Contaminant Type
Soil
Groundwater
Surface Water
Air
Sediment
Bedrock
Halogenated Organics - Halogenated Organics C
Metals - Metals Priority Pollutants C C B
Halogenated Organics - Polychlorinated biPhenyls (PCB) B
Non-Halogenated Organics - Petroleum Products-Unspecified B
Non-Halogenated Organics - Polycyclic Aromatic Hydrocarbons C B
Metals - Arsenic C C
Non-Halogenated Organics - Organotins B
Metals - Lead C
Non-Halogenated Organics - Petroleum-Diesel C C
Non-Halogenated Organics - Petroleum-Other C
S
Suspected
C
Confirmed Above Cleanup Levels
B
Below Cleanup Levels
RA
Remediated-Above
RB
Remediated-Below
R
Remediated
This contaminant list was based on our best information at the time it was entered. It may not reflect current conditions at the site.