Facility Site ID: 2899
Cleanup Site ID: 219

Current Status

Whatcom Waterway cleanup site map (click to enlarge)
Whatcom Waterway cleanup site map (click to enlarge)

Last Updated: September 2025

2023 Fact SheetInformación en español

The Department of Ecology (Ecology) is overseeing the cleanup of the Whatcom Waterway site on the Bellingham waterfront. Ecology held a 30-day comment period (April 24 - May 23, 2023) on the following documents:

We received 12 comments and responded to them in our Response to Comments Summary document. No significant changes were made to the documents, and they were finalized.

Estimated Site Timeline

  • 2023: Begin designing the cleanup (engineering design) for the remaining Phase 2 Site Areas
  • 2024 - 2025: Construction of the Bellingham Shipping Terminal dredging project
  • 2026 - 2028: Construction of the cleanup action for the remaining Phase 2 Site Areas 

Sign Up For Updates!

Join our email list to receive updates about the Whatcom Waterway cleanup site. Email Kristen Forkeutis, Public Involvement Coordinator, at Kristen.Forkeutis@ecy.wa.gov to be added to the list. Unsubscribe at any time.

General Cleanup Process

The Model Toxics Control Act (MTCA) is Washington’s environmental cleanup law. It provides requirements for contaminated site cleanup and sets standards that protect human health and the environment. Ecology enacts MTCA and oversees cleanups. The MTCA site cleanup process is completed in steps over a variable timeline.

Public Participation

Current Whatcom Waterway cleanup site Public Participation Plan

This plan describes how Ecology will share information with the community and how you can share information with us. Ecology will review this plan as the cleanup progresses and amend/update it as necessary. 

Cleanup Status

Aerial Map of Whatcom Waterway Site Areas (Click to enlarge)
Aerial Map of Whatcom Waterway Site Areas (Click to enlarge)

Log Pond Area - Cleanup Completed
In November 2000, Georgia-Pacific, with Ecology oversight, began construction activities to address contaminated sediment within the Log Pond area of the site. About 43,000 cubic yards of clean material were placed over 5.6 acres to cover contaminated sediment and restore habitat. Construction concluded in February 2001.

To ensure the completed cleanup protects human health and the environment in the long term, scientists are conducting physical, chemical, and biological monitoring. Based on monitoring results, additional material was placed along some shoreline areas of the Log Pond to prevent erosion as part of the cleanup for the Phase 1 Site Areas described below.  

Phase 1 Site Areas - Cleanup Completed
In July 2015, the Port of Bellingham, with Ecology oversight, began construction activities to address contaminated sediment within the Phase 1 Site Areas. The work was completed in 2016 and included:

  • Removing 111,446 cubic yards of contaminated sediment
  • Removing 9,962 tons of soil and 265 tons of creosote-treated timber
  • Removing 5,146 tons of concrete and asphalt rubble (over 98% was reused or recycled)
  • Isolating contaminated sediment with 102,950 cubic yards of clean material
  • Installing 36,600 square feet of sheet pile walls on the north side of the waterway to support the upland and prevent contaminated groundwater from entering the waterway

To ensure the completed cleanup protects human health and the environment in the long term, scientists are conducting physical, chemical, and biological monitoring.

Monitored Natural Recovery Areas
Monitoring of the completed cleanup for the Phase 1 Site Areas also includes chemical monitoring of natural recovery areas. This ensures that contaminated sediment isolated by clean material (due to natural processes) remains isolated.

Phase 2 Site Areas - Cleanup Underway
In 2023, Ecology amended the existing Cleanup Action Plan (CAP) for the Phase 2 Site Areas. The CAP amendment is part of a legal agreement (consent decree) between Ecology, the Port, the City, and the DNR. The CAP amendment included these actions:

  • Sequences design and construction activities to prioritize early cleanup at the Bellingham Shipping Terminal (BST).
  • Records a possible future change to the cleanup action at the head of the Whatcom Waterway to provide habitat benefit.
  • Revises the cleanup action for the Aeration Stabilization Basin (ASB), including dredged material disposal, due to changes in land use plans.
  • Adds a cleanup standard for dioxin and furan compounds due to regulatory changes.

Site Information

Whatcom Waterway site, Bellingham waterfront, May 2019
Whatcom Waterway site, Bellingham waterfront, May 2019

Background
The 700+ acre site is located within Bellingham Bay south of the Holly Street bridge in Bellingham, Washington. Most of the site is owned by the State of Washington. 

The cleanup of the Log Pond Area (6 acres) was completed in 2001, and Phase 1 Site Areas (18 acres) was completed in 2016. Monitoring of these areas and natural recovery areas (636 acres) continues. The cleanup of Phase 2 Site Areas (71 acres) remains to be performed. 

Contamination
The site includes in-water sediment impacted by contaminants released from past industrial waterfront activities, including discharges from the former Georgia-Pacific chlor-alkali plant, wood waste and degradation products from historic log rafting activities, and pulp mill wastewater discharges.  

As a result of these past industrial activities, studies conducted as part of the cleanup process have shown mercury, 4-methyphenol, and dioxin/furan compounds in sediment at concentrations that exceed the requirements of the state’s cleanup law, the Model Toxics Control Act (MTCA), and must be addressed.

Bellingham Bay Action Team
The Whatcom Waterway site is one of 12 sites coordinated through the Bellingham Bay Action Team (BBAT). BBAT is a bay-wide multi-agency effort to clean up contaminated sediment, control sources of sediment contamination, and restore habitat, with consideration for land and water uses. In 2000, participants in this initiative developed the Bellingham Bay Comprehensive Strategy.

Language Services

Need help or have questions? We offer translation and interpretation services at no cost. If you need these services, email kristen.forkeutis@ecy.wa.gov or call 425-240-4353. If you call, ask for an interpreter to be connected with one.

Español

Le ofrecemos servicios de traducción e interpretación sin costo. Para solicitar una copia de esta información en español, llame a Kristen Forkeutis al 425-240-4353 o envíe un correo electrónico a kristen.forkeutis@ecy.wa.gov. Si necesita servicios de interpretación, solicite un intérprete y permanezca en la línea mientras lo comunicamos.
Legal 11
Map 1
Document Title Document Date Document Type
Site Map 11/2/1915 Map
Outreach Information 17
Document Title Document Date Document Type
Whatcom Waterway - Environmental Justice Assessment Postcard 2/4/2026 Fact Sheet\Public Notices
Whatcom Waterway - PPP 7/13/2023 Public Participation Plan
Whatcom Waterway - Response to Comments CD, CAP & PPP 7/13/2023 Responsiveness Summary
Whatcom Waterway - Fact Sheet CD, CAP & PPP 4/10/2023 Fact Sheet\Public Notices
Whatcom Waterway - Postcard CD, CAP & PPP 4/10/2023 Fact Sheet\Public Notices
Whatcom Waterway - Responsiveness Summary EDR Phase 1 11/19/2013 Responsiveness Summary
Whatcom Waterway - Fact Sheet EDR Phase 1 2/26/2013 Fact Sheet\Public Notices
Whatcom Waterway - Responsiveness Summary CD Amend 8/11/2011 Responsiveness Summary
Whatcom Waterway - Fact Sheet CD Amend, Extension 3/24/2011 Fact Sheet\Public Notices
Whatcom Waterway - Fact Sheet CD Amend 3/11/2011 Fact Sheet\Public Notices
Whatcom Waterway - Presentation CD Amend 3/11/2011 Fact Sheet\Public Notices
Whatcom Waterway - Responsiveness Summary CD 9/1/2007 Responsiveness Summary
Whatcom Waterway - Fact Sheet CD 7/1/2007 Fact Sheet\Public Notices
Whatcom Waterway - Fact Sheet RI/FS 10/1/2006 Fact Sheet\Public Notices
Whatcom Waterway - Fact Sheet Two AOs 3/1/2005 Fact Sheet\Public Notices
Whatcom Waterway - Fact Sheet AO for IA 4/1/2002 Fact Sheet\Public Notices
Whatcom Waterway - Fact Sheet FS and EIS 3/1/2002 Fact Sheet\Public Notices
State Environmental Policy Act 5
Technical Reports 66
Document Title Document Date Document Type
Whatcom Waterway - Revised EDR: Unit 1C Dredging 8/18/2025 Engineering Design Report
Whatcom Waterway - Change of Designated Project Coordinator - Rapp 8/18/2025 Site Specific Administrative Document - Other (Administrative Correspondence)
Whatcom Waterway - Revised EDR: Unit 1C Dredging 6/17/2024 Engineering Design Report
Whatcom Waterway - SHARP Report 5/16/2024 Site Hazard Assessment and Ranking Process Report
Whatcom Waterway - Change of Designated Project Coordinator 5/15/2024 Site Specific Administrative Document - Other (Administrative Correspondence)
Whatcom Waterway - CAP 2nd Amend 3/27/2024 Cleanup Action Plan
Whatcom Waterway - EDR: Phase 2 Areas - Unit 1C Dredging 12/8/2023 Engineering Design Report
Whatcom Waterway - Phase 1 Areas Year 5 Compliance Monitoring Report, Text, Tables and Figures 4/27/2022 Monitoring Report
Whatcom Waterway - Phase 2 Areas Pre-Remedial Design Investigation Data Report 5/11/2021 Site Specific Technical Document - Other
Whatcom Waterway - PRI Work Plan, Addendum No. 3 8/19/2020 Remedial Investigation Work Plan
Whatcom Waterway - Phase 1 Areas Year 3 Compliance Monitoring Report 7/20/2020 Monitoring Report
Whatcom Waterway - Phase 1 Areas Year 1 Compliance Monitoring Report 5/13/2019 Monitoring Report
Whatcom Waterway - Phase 1 Areas As-Built Report, Tables, and Figures 9/30/2018 Remedial Action/As-Built Report
Whatcom Waterway - Phase 1 Areas As-Built Report, Appendices A-B 9/30/2018 Remedial Action/As-Built Report
Whatcom Waterway - Phase 1 Areas As-Built Report, Appendix C 9/30/2018 Remedial Action/As-Built Report
Whatcom Waterway - Phase 1 Areas As-Built Report, Appendices D-M 9/30/2018 Remedial Action/As-Built Report
Whatcom Waterway - Institutional Control Plan Phase 1 Site Areas 6/1/2018 Operation and Maintenance Plan
Whatcom Waterway - Sampling and Quality Assurance Project Plan for Compliance Monitoring - Phase 1 6/16/2016 Sampling and Analysis Plan
Whatcom Waterway - Final EDR Phase 1 4/10/2015 Engineering Design Report
Whatcom Waterway - Final EDR Phase 1 Appendix A-E 4/10/2015 Engineering Design Report
Whatcom Waterway - Final EDR Phase 1 Appendix F-I 4/10/2015 Engineering Design Report
Whatcom Waterway - Final EDR Phase 1 Appendix J-N 4/10/2015 Engineering Design Report
Whatcom Waterway - Final EDR Phase 1 Figures 1-11 4/10/2015 Engineering Design Report
Whatcom Waterway - Final EDR Phase 1 Figures 12a-17c 4/10/2015 Engineering Design Report
Whatcom Waterway - Phase 1 Areas Design Specifications 5/22/2013 Site Specific Technical Document - Other
Whatcom Waterway - Phase 1 Areas Design Drawings, Part 1 5/20/2013 Site Specific Technical Document - Other
Whatcom Waterway - Phase 1 Areas Design Drawings, Part 2 5/20/2013 Site Specific Technical Document - Other
Whatcom Waterway & Central Waterfront - Shoreline Design Investigation 10/19/2012 Site Specific Technical Document - Other
Whatcom Waterway - preliminary design concept report 8/1/2012 Construction Plans and Specifications
Whatcom Waterway & Central Waterfront - Work Plan Addendum 7/12/2012 Site Specific Technical Document - Other
Whatcom Waterway - CAP 1st Amend 8/19/2011 Cleanup Action Plan
Whatcom Waterway - PRDI Data Report - with figures 8/1/2010 Remedial Investigation Report
Whatcom Waterway - CAP 9/24/2007 Cleanup Action Plan
Whatcom Waterway - Supplemental RI/FS -Volume 1, RI 10/10/2006 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - Supplemental RI/FS - Volume 1, RI, Appendix I - Year 5 monitoring report 10/10/2006 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - Supplemental RI/FS - Volume 1, RI, Appendix B - Data summaries 10/10/2006 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - Supplemental RI/FS - Volume 1, RI, Appendix C - 2003 ASB Sampling Data 10/10/2006 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - Supplemental RI/FS - Volume 1, RI, Appendix D - 2004 ASB sludges & berm sands - Test Results 10/10/2006 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - Supplemental RI/FS - Volume 1, RI, Appendix E - Data used to develop site-specific mercury bioaccumulation screening levels 10/10/2006 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - Supplemental RI/FS - Volume 1, RI, Appendix F - Colony Wharf sediment sampling report 10/10/2006 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - Supplemental RI/FS - Volume 1, RI, Appendix G - Tables of enrichment ratio summaries 10/10/2006 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - Supplemental RI/FS - Volume 1, RI, Appendix H - Previous PSDDA characterization analyses 10/10/2006 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - Supplemental RI/FS - Volume 1, RI, Appendix A - Pre-remedial design evaluation report (2003) 10/10/2006 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - Supplemental RI/FS -Volume 2, FS 10/10/2006 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - Supplemental RI/FS-Volume 2, FS, Appendix A 10/10/2006 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - Supplemental RI/FS -Volume 2, FS, Appendix B 10/10/2006 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - Supplemental RI/FS -Volume 2, FS, Appendix C 10/10/2006 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - Supplemental RI/FS -Volume 2, FS, Appendix D 10/10/2006 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - IA, Log Pond Cleanup, Habitat Restoration Project - Monitoring Report Year 2 12/1/2002 Interim Action Plans and Reports
Whatcom Waterway - Response to Comments on Draft Supplemental FS and EIS 10/1/2002 Site Specific Administrative Document - Other (Administrative Correspondence)
Whatcom Waterway - Supplemental FS 3/1/2002 Feasibility Study
Whatcom Waterway - IA, Log Pond Cleanup, Habitat Restoration Project - Monitoring Report Year 1 12/1/2001 Interim Action Plans and Reports
Whatcom Waterway - Log Pond Cleanup, Habitat Restoration Project, Completion Report, Part 1 5/29/2001 Interim Action Plans and Reports
Whatcom Waterway - Log Pond Cleanup, Habitat Restoration Project, Completion Report, Part 2 5/29/2001 Interim Action Plans and Reports
Whatcom Waterway - Log Pond Cleanup, Habitat Restoration Project, Completion Report, Part 3 5/29/2001 Interim Action Plans and Reports
Whatcom Waterway - RI/FS Report - Vol. 1 Part 1 7/25/2000 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - RI/FS Report - Vol. 1 Part 2 7/25/2000 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - RI/FS Report - Vol. 2 7/25/2000 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - RI/FS Report - Vol. 3 Part 1 7/25/2000 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - RI/FS Report - Vol. 3 Part 2 7/25/2000 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - RI/FS Report - Vol. 3 Part 3 7/25/2000 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - RI/FS Report - Vol. 3 Part 4 7/25/2000 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - RI/FS Report - Vol. 4 Part 1 7/25/2000 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - RI/FS Report - Vol. 4 Part 2 7/25/2000 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - RI/FS Report - Vol. 4 Part 3 7/25/2000 Remedial Investigation / Feasibility Study Report
Whatcom Waterway - RI/FS Report - Vol. 4 Part 4 7/25/2000 Remedial Investigation / Feasibility Study Report
There may be more documents related to this site. To obtain documents not available electronically, you will need to make a public records request.

Places to see print documents

  • Northwest Regional Office
    15700 Dayton Ave N
    Shoreline, 98133
    Please schedule an appointment to view print documents at this location.
  • Ecology Bellingham Field Office
    913 Squalicum Way, Unit 101
    Bellingham, 98225
    This location may only have print documents available during open comment periods.
  • Bellingham Public Library
    210 Central Ave
    Bellingham, 98225
    This location may only have print documents available during open comment periods.

Contaminants 10

Contaminant Type
Soil
Groundwater
Surface Water
Air
Sediment
Bedrock
Other Contaminant - Base/Neutral/Acid Organics B B B
Halogenated Organics - Halogenated Organics B B B B
Metals - Metals Priority Pollutants B B B B C
Halogenated Organics - Polychlorinated biPhenyls (PCB) B
Non-Halogenated Organics - Petroleum Products-Unspecified B B B
Non-Halogenated Organics - Phenolic Compounds B B B C
Non-Halogenated Organics - Polycyclic Aromatic Hydrocarbons B B B
Other Contaminant - Conventional Contaminants, Organic B B B B
Other Contaminant - Conventional Contaminants, Inorganic B B B B
Other Contaminant - Other Deleterious Substances C
S
Suspected
C
Confirmed Above Cleanup Levels
B
Below Cleanup Levels
RA
Remediated-Above
RB
Remediated-Below
R
Remediated
This contaminant list was based on our best information at the time it was entered. It may not reflect current conditions at the site.