The work will include:
After system construction, testing, and startup, the system will be operated and maintained. Sampling will be conducted during system operation to evaluate ongoing treatment system effectiveness.
General Cleanup Process
The Model Toxics Control Act (MTCA; Chapter 70.105D RCW) is Washington’s environmental cleanup law. It provides requirements for contaminated site cleanup and sets standards that protect human health and the environment. Ecology enacts the MTCA and oversees cleanups. The MTCA site cleanup process is completed in steps (see graphic) over a variable timeline.
Site Information
The Site is located at 2350 24th Avenue East, Seattle, WA. The Property is located in a mixed commercial area of the Montlake residential neighborhood.
A former Circle K service station operated on the Site from 1968 until 1990. Currently The property consists of a one-story building and a newer addition to it, which are presently being utilized as a retail dry-cleaning store and a convenience store, known as Jay’s Cleaners and Mont’s Market.
1989: Petroleum contamination was discovered in both soil and groundwater due to a leaking underground storage tank. Approximately 4,000 to 6,000 gallons of gasoline was released. In October, six underground storage tanks and 900 cubic yards of contaminated soil were excavated.
1990: The gasoline pump island was demolished. The gasoline pump island was demolished.
1992: Ecology and a new property owner entered into a Mixed Funding Consent Decree where Ecology provided the property owner a loan from state funds to cover a portion of the cleanup costs. Ecology conducted an early cleanup action, called an interim action. Ecology’s interim action:
o Removed leaking tanks
o Conducted partial soil evacuation
o Installed a product recovery system that operated until 1997
2005: Ecology conducted Pilot Study tests in 2005 and in 2017 to evaluate other potential cleanup alternative for remaining contamination.
2006: Results from the November groundwater monitoring showed presence of free products in two wells located within the property and two wells located on East McGraw Street.
2017: Ecology conducted another Pilot Study test
2018: Ecology held a 30-day public comment period on the draft Remedial Investigation, draft Feasibility Study, draft Cleanup Action Plan, and State Environmental Policy Act.
Contamination
In 2017 Ecology completed an environmental study (Remedial Investigation/Feasibility Study, RI/FS) of the Site and assessed a range of cleanup options.
The study found chemicals in soil and groundwater from a former service station and lube facility:
· Petroleum products (Gasoline, Diesel, Oil-range Total Petroleum Hydrocarbons)
· Benzene, Toluene, Ethyl-Benzene, and Xylene (BTEX)
The petroleum plume has extended off-property beneath adjacent streets and residential property.
Public Participation
Current Circle K 1461 cleanup site Public Participation Plan
This plan includes information for the public regarding opportunities to get involved in the cleanup process. The outreach activities and mechanisms presented reflect Ecology’s current plans for keeping the public informed and for receiving information and comments from the public.
Documents 80
Legal 6
Document Title | Document Date | Document Type |
Circle K 1461 - Release of Lien | 3/7/2008 | Lien related document |
Circle K Chapter 11 Settlement Agreement | 3/26/1993 | Settlement Agreement (court allocated liability) |
Circle K 1461 Consent Decree | 4/9/1992 | Consent Decree |
Circle K Station 1461 | 4/8/1992 | Consent Decree |
Circle K Station #1461 - Consent Decree | 4/8/1992 | Consent Decree |
1991_March_20_DOE_Early_Notice_Letter.pdf | 3/20/1991 | Early Notice Letter |
Map 1
Document Title | Document Date | Document Type |
Site Map | 9/16/2016 | Map |
Public Information 13
Document Title | Document Date | Document Type |
Circle K 1461 - Response to Comments Summary - October 2018 | 10/26/2018 | Responsiveness Summary |
Circle K 1461 - Public Participation Plan - September 2018 | 8/29/2018 | Public Participation Plan |
Circle K 1461 - Fact Sheet draft RI/FS, draft CAP, SEPA checklist/DNS - September 2018 | 8/29/2018 | Fact Sheet\Public Notices |
Circle K 1461 - Construction Flier Sept 23 2016 | 9/22/2016 | Fact Sheet\Public Notices |
Circle K 1461 - Construction Flier Sept 23, 2016 | 9/22/2016 | Fact Sheet\Public Notices |
1992_Jan_Fact_Sheet.pdf | 1/31/2016 | Fact Sheet\Public Notices |
1992_Feb_25_Responsiveness_Summary | 2/25/1992 | Responsiveness Summary |
1991_Dec_Fact_Sheet000.pdf | 12/31/1991 | Fact Sheet\Public Notices |
1991_Dec_Fact_Sheet.pdf | 12/31/1991 | Fact Sheet\Public Notices |
Determination_of_Nonsignificance.pdf | 12/20/1991 | Fact Sheet\Public Notices |
1991_DEC_13_Repository_Check_List | 12/13/1991 | Public Participation Plan |
1991_Dec_11_PPP | 12/11/1991 | Public Participation Plan |
1991_Dec_11_mailing_list | 12/11/1991 | Public Participation Plan |
State Environmental Policy Act 4
Document Title | Document Date | Document Type |
Executive Order 05-05 Circle K 1461 Final Determination | 11/28/2018 | SEPA Documents |
Circle K 1461 Cleanup Site Public Inadvertent Discovery Plan 9-17-2018 | 9/17/2018 | SEPA Documents |
Circle K 1461 DNS 9-17-2018 | 9/17/2018 | SEPA Documents |
Circle K 1461 SEPA Chectlist 08-28-2018 | 8/28/2018 | SEPA Documents |
Technical Reports 56
Document Title | Document Date | Document Type |
Final Circle K EDR Addendum 11-21-2023 | 11/21/2023 | Engineering Design Report |
Circle K 1461 O&M Manual 03-30-2023 | 3/30/2023 | Operation and Maintenance Plan |
Circle K Compliance Monitoring Plan CMP Final 20221122 | 11/22/2022 | Site Specific Technical Document - other |
Circle K A-E Services Progress Report 05/27/2022 | 5/27/2022 | Progress Report |
Circle K A-E Services Progress Report 04/29/2022 | 4/29/2022 | Progress Report |
Circle K A-E Services Progress Report 04/01/2022 | 4/1/2022 | Progress Report |
Circle K A-E Services Progress Report 02252022 | 2/25/2022 | Progress Report |
Circle K 1461 Final EDR 12-10-2021 Appendices | 12/10/2021 | Engineering Design Report |
Circle K 1461 Final EDR 12-10-2021 TextTablesFigs | 12/10/2021 | Engineering Design Report |
Circle K Ecology response to Young-Do Inquiry 10-22-2019 | 10/22/2019 | Site Specific Administrative Document - other (Administrative correspondence) |
Circle K 1461 Informational Meeting for A-E Project Support 10-03-2019 | 9/30/2019 | Site Specific Administrative Document - other (Administrative correspondence) |
Circle K 1461 CLEANUP ACTION PLAN cover page final explanation | 11/18/2018 | Cleanup Action Plan |
Circle K 1461 CLEANUP ACTION PLAN cover page final | 11/17/2018 | Cleanup Action Plan |
Circle K 1461 Preliminary Draft CAP 12-18-2017 | 12/18/2017 | Cleanup Action Plan |
Circle K 1461 Draft RI-FS Report 12-14-2017 | 12/14/2017 | Remedial Investigation / Feasibility Study |
Circle K 1461 UIC Well Registration for insitu FS Pilot Study (signed) 02-08-2017 | 2/8/2017 | Site Specific Technical Document - other |
Circle K 1461 Pilot Study Work Plan 02-01-2017 | 2/1/2017 | Site Specific Technical Document - other |
IDW Soil-Water Profiles signed 10-27-2016 | 10/27/2016 | Site Specific Technical Document - other |
Circle K Access Agreement 2415 E McGraw Street | 6/20/2016 | Site Specific Administrative Document - other (Administrative correspondence) |
Circle K STA 1461 Remedial Investigation Sampling and Analysis Work Plan 04-07-2016 | 4/7/2016 | Remedial Investigation Work Plan |
Circle K 1461 - Remedial Investigation Work Plan | 4/7/2016 | Remedial Investigation Work Plan |
Summary of Subsurface Investigations Montlake Neighborhood Former Dry Cleaner | 5/29/2013 | Site Specific Technical Document - other |
Draft RI.FS WADOE October 2009 | 10/31/2009 | Remedial Investigation / Feasibility Study |
2009_Sept_Rem_Invest_Feas_report_DRAFT | 9/30/2009 | Remedial Investigation / Feasibility Study |
2007_Oct_10_Ecovac_EFR Surfactant Injection Proposal | 10/15/2007 | Interim Action Documents |
2006_Nov_21_EA_Eng_GW_monitoring | 11/21/2006 | Groundwater Monitoring Report |
2006_Nov_7_EA_Eng_GW_monitoring | 11/7/2006 | Groundwater Monitoring Report |
2006_Aug_14_EA_Eng_GW_monitoring | 8/14/2006 | Groundwater Monitoring Report |
2006_Feb_16_EA_Eng_GW_Data_summary | 2/16/2006 | Groundwater Monitoring Report |
2005_June_Investigation_Report | 6/30/2005 | Site Specific Technical Document - other |
2005_June_13_EcoVac_EFR_Pilot Test Results | 6/13/2005 | Interim Action Documents |
2005_May_11_EA_Eng_GW_monitoring | 5/11/2005 | Groundwater Monitoring Report |
2003_Nov_26_Field_Investigation | 11/26/2003 | Site Specific Technical Document - other |
2002_July_18_Cleanup_Activity_Updates | 7/18/2002 | Interim Action Documents |
2002_June_19_DOE_letter_to_D._Camille | 6/19/2002 | Site Specific Administrative Document - other (Administrative correspondence) |
2001_April_25_Glacier_lab_report | 4/25/2001 | Interim Action Documents |
2001_Jan_15_Glacier_Discharge_Auth | 1/15/2001 | Site Specific Technical Document - other |
2000_19_Dec_Proposal_fo_GW_Monitoring.pdf | 12/19/2000 | Groundwater Monitoring Report |
2000_Dec_6_DOE_letter_to_J.Choung.pdf | 12/6/2000 | Site Specific Administrative Document - other (Administrative correspondence) |
2000_Jan_11_Glacier_Interim_Report | 1/11/2000 | Interim Action Documents |
1998_July_7_Glacier_Interim_Field_Report | 7/7/1998 | Interim Action Documents |
1995_June_9_DOH_Health_Investgation.pdf | 6/9/1995 | Human Health and/or Eco Risk Assessment |
1994_Aug_5_DOE_letter_to_J.Chuong.pdf | 8/5/1994 | Site Specific Administrative Document - other (Administrative correspondence) |
1994_Aug_5_DOE_letter_to_G.Renale.pdf | 8/5/1994 | Site Specific Administrative Document - other (Administrative correspondence) |
Circle K 1461 - Site Hazard Assessment | 6/30/1994 | Site Hazard Assessment Report |
Bankruptcy Court Circle K Settlement Agreement | 4/2/1993 | Site Specific Administrative Document - other (Administrative correspondence) |
1992_June_1_Glacier_First_phase_report.pdf | 6/1/1992 | Site Specific Technical Document - other |
1992_June_1_Glacier_Report_first_phase | 6/1/1992 | Interim Action Documents |
Circle K 1461 - Site Hazard Assessment | 1/1/1991 | Site Hazard Assessment Report |
1990_Nov_12_Geo_Eng_Progress_rpt_#2 | 11/12/1990 | Interim Action Documents |
Progress Report August 23 1990 | 8/23/1990 | Progress Report |
1990_Aug_23_Geo_Eng_Progress_rpt_#1 | 8/23/1990 | Groundwater Monitoring Report |
1990_March_6_Geo_Engineers_geotech_rpt | 3/6/1990 | Progress Report |
1990_March_6_Geo_Engineers_geotech_rpt | 3/6/1990 | Site Specific Technical Document - other |
1990_March_6_Geo_Engineers_report | 3/6/1990 | Groundwater Monitoring Report |
CircleK Boring Logs Historical | 1/9/1990 | Site Specific Technical Document - other |
Places to see print documents
-
Northwest Regional Office15700 Dayton Ave NShoreline, 98133Please schedule an appointment to view print documents at this location.
-
Seattle Public Library - Montlake Branch2401 24th Avenue EastSeattle, 98112This location may only have print documents available during open comment periods.
Contaminants 3
Contaminant Type | Soil |
Groundwater |
Surface Water |
Air |
Sediment |
Bedrock |
---|---|---|---|---|---|---|
Non-Halogenated Organics - Non-Halogenated Solvents | C | C | ||||
Non-Halogenated Organics - Benzene | C | C | ||||
Non-Halogenated Organics - Petroleum-Gasoline | C | C |
- S
- Suspected
- C
- Confirmed Above Cleanup Levels
- B
- Below Cleanup Levels
- RA
- Remediated-Above
- RB
- Remediated-Below
- R
- Remediated