Document Repository for CUSTOM PLYWOOD MILL
 Document TitleDocument DateBusiness TypeLink

Group: Legal

 In the Matter of Remedial Action by: G B H Investments, LCC03/11/2008Agreed OrderShow
 Custom Plywood- Lien 04/02/2012Lien related documentShow

Group: Public Information

 Custom Plywood Mill Public Participation Plan01/28/2011Public Participation PlanShow
 Custom Plywood Mill Fact Sheet February 201102/11/2011Fact Sheet\Public NoticesShow
 Custom Plywood Final Fact Sheet August 201208/14/2012Fact Sheet\Public NoticesShow
 Custom Plywood Mill Updated Public Participation Plan August 201208/14/2012Public Participation PlanShow
 Custom Plywood Summay Response to Comments on Draft Cleanup Action Plan and Engineering Design Report February 2013 02/20/2013Responsiveness SummaryShow
 Custom Plywood Mill Public Participation Plan February 201902/04/2019Public Participation PlanShow
 Custom Plywood Final Fact Sheet March 201903/07/2019Fact Sheet\Public NoticesShow

Group: State Environmental Policy Act

 Custom Plywood Mill Draft SEPA February 201102/08/2011SEPA DocumentsShow
 Custom Plywood Mill SEPA Checklist and Mitigated Determination of Non-Significance for Phase II August 201208/15/2012SEPA DocumentsShow
 Custom Plywood SEPA Notice and Checklist March 201903/07/2019SEPA DocumentsShow

Group: Technical Reports

 Underwater Habitat Survey, Anacortes Custom Plywood Benthic Study, November 200711/30/2007Site Specific Technical Document - otherShow
 Custom Plywood Mill Historical Evaluation of the Tugboat Enchantress06/01/2008Independent ReportsShow
 Remedial Investigation/Feasibility Study Work Plan, Final, September 200809/30/2008Remedial Investigation / Feasibility StudyShow
 Biological Evaluation, Emergency Action Project, March 201003/01/2010Site Specific Technical Document - otherShow
 Appendix C, Chemistry Laboratoty Reports and Chain-of-Custody Forms, June 201006/30/2010Site Specific Technical Document - otherShow
 Appendix C-2, Chain of Custody Forms, Custom Plywood Mill, June 201006/30/2010Site Specific Technical Document - otherShow
 Custom Plywood Mill Open House Public Meeting Presentation March 201103/11/2011Site Specific Administrative Document - other (Administrative correspondence)Show
 Custom Plywood Final Construction Management Plan07/07/2011Engineering Design ReportShow
 Custom Plywood Mill Final Feasibility Study Report for Interim Action Work Plan September 201109/29/2011Feasibility StudyShow
 Custom Plywood Mill Final Remedial Investigation Report Part 1 September 201109/29/2011Remedial Investigation ReportShow
 Custom Plywood Mill Final Remedial Investigation Report Part 2 September 201109/29/2011Remedial Investigation ReportShow
 Custom Plywood Mill Final Remedial Investigation Report Part 2 September 201109/29/2011Remedial Investigation ReportShow
 Custom Plywood Mill Final Remedial Investigation Report Part 4 September 201109/29/2011Remedial Investigation ReportShow
 Custom Plywood Mill Final Upland Remediation (Phase I) Cleanup Action Plan for Interim Action Work Plan September 201109/29/2011Cleanup Action PlanShow
 Custom Plywood Mill Final Upland Remediation (Phase I) Engineering Design Report for Interim Action Work Plan September 201109/29/2011Engineering Design ReportShow
 Custom Plywood Mill Summary Response to Public Comment on Interim Action Draft September 201109/29/2011Site Specific Administrative Document - other (Administrative correspondence)Show
 Human Health Risk Assessment Addendum for the Custom Plywood Interim Action Work Plan 07/02/2012Interim Action DocumentsShow
 Custom Plywood Mill Final Summary Response to Public Comments on Interim Action August 201208/14/2012Interim Action DocumentsShow
 Custom Plywood Final Cleanup Action Plan and Engineering Design Report February 201302/19/2013Cleanup Action PlanShow
 Custom Plywood Thin Layer Capping Pilot Study July 201208/01/2014Remedial Investigation ReportShow
 Custom Plywood Phase III - Cleaup Action Plan and Engineering Design Report February 201902/13/2019Cleanup Action PlanShow
 Custom Plywood Thin Layer Cap Pilot Study - Ecology Revised February 201902/19/2019Remedial Investigation Work PlanShow