Status Update
Ecology held a public comment period from October 10 - November 8, 2024 for the Interim Action Work Plan – Phase 2 Removal Action. The document describes how cleanup of contamination from former waste piles will be conducted at the Site.
Ecology did not receive any public comments during the comment period. The liable party will continue to clean up the Site under the Agreed Order.
Model Toxics Control Act Cleanup Process
The Model Toxics Control Act (MTCA) is Washington’s environmental cleanup law. It provides requirements for contaminated site cleanup and sets standards that protect human health and the environment. Ecology implements the law and oversees cleanups.
The MTCA site cleanup process is completed in steps over a variable timeline.
Proposed Cleanup Timeline
Estimated Timeline
2024: Phase 2 Interim Action
2024-2025: Implementation of Remedial Investigation.
2025: Perform the Feasibility Study
2026: Prepare the Draft Cleanup Action Plan
Each of the remaining cleanup process steps will require a public comment period. The graphic above shows these different stages of cleanup. Sometimes multiple stages occur in one public comment period.
Planned Redevelopment
The Owner plans to redevelop the property as a warehouse following the Phase 2 interim cleanup action including:
- Demolition of all existing structures (some demolition will occur in conjunction with the cleanup).
- Construction of an approximate 178,700 square foot warehouse building with concrete and asphalt loading dock, roads, and parking area.
- Installation of new stormwater facility and new utility connections.
ksiekawitch@bridgeindustrial.com or call 425-749-4325.
Wetland Mitigation
Portions of the western wetland and portions of the on-property ditch will be filled, and a new wetland will be created along the eastern portion of the property.
For more information on wetlands can also be found on the Ecology Wetlands Webpage.
State Environmental Policy Act For The Redevelopment
The City of Kent is the lead agency for the State Environmental Policy Act SEPA for the redevelopment activity. The SEPA includes remedial investigation and interim action activities as part of the Ecology-supervised cleanup. In September 2024, a Modified Mitigated Determination of Non-Significant (MMDNS) was issued. For more information, please contact Nate Schildmeyer, AICP at 253-856-5454, email nschildmeyer@KentWA.gov or mail to 220 4th Ave South, Kent WA, 98032.
Phase 1 Interim Action
Cleanup work at the Maralco site started in 2023 under Ecology’s Voluntary Cleanup Program (VCP). The VCP provides technical help to owners of contaminated sites to fulfill the Model Toxics Control Act (MTCA) cleanup standards while undergoing cleanup independent of Ecology oversight.
As a part of the independent cleanup, the dross and other stockpiled wastes on the property and inside the building were removed. This removal was Phase 1 of the interim action and was conducted from August 2023 to November 2023. Approximately 35,300 tons of waste were removed from the Site during the Phase 1 interim action.
After the waste piles and dross were removed, surface soil samples were collected from the area beneath the removed stockpiles. Sample results showed that residual dross and/or contaminated soil was present in the drainage ditches. The contaminated soil beneath the former dross pile and within the ditches that was not cleaned up under Phase 1 of the interim action will be cleaned up during Phase 2.
Site Location
Site Background
Several waste piles remained on the property from the smelting operation (see photos to right) until the Phase 1 interim action was performed in 2023. Other by-products such as the aluminum oxide were also stockpiled on the property and inside the smelter building.
Site Pictures
Maralco property aerial photo (2023)
Maralco property and wetlands (2023)
Abandoned smelter building (2023)
Maralco property aerial photo (1993)
Contamination
Investigations through 2023 found the following contaminants of concern on the property:
- Soil: Metals, total petroleum hydrocarbons (TPH) from diesel fuel
- Groundwater: Metals, TPH, chloride, fluoride, and ammonia
Metals were also found in soil in the offsite drainage ditch located north of the property.
Public Participation
Working With Tribes
We engage with Tribes both in formal government-to-government relationships and through broader outreach whenever cleanup activities or contamination discoveries may affect tribal interests and resources. This engagement provides opportunities for tribal input throughout the cleanup process.
Ecology also works closely with the Department of Archaeology and Historic Preservation to ensure that any ground-disturbing activities comply with state and federal historical and archaeological preservation laws.
Environmental Justice
Learn How Ecology Is Protecting The Environment In Your Community
What's In My Neighborhood shows contamination cleanup sites in Washington state. Ecology encourages cleanup of these sites to protect the health of people, plants, and animals. Cleanups are projects that remove, treat, or contain potentially harmful substances.
Report An Environmental Issue
Counties: Island, King, Kitsap, San Juan, Skagit, Snohomish, and Whatcom
Email: nwroerts@ecy.wa.gov
Phone: 206-594-0000
Requesting Accommodation
If you speak a non-English language, free language services are available.
Translated Content
Bộ Môi Sinh (Ecology) đang công bố thời gian lấy ý kiến công chúng liên quan đến việc tẩy nhiễm môi trường tại địa điểm Maralco. Để truy cập tài liệu này hoặc để biết thêm thông tin về địa điểm này bằng tiếng Việt, vui lòng liên lạc Liêm Nguyễn tại 360-790-4730 hoặc email liem.nguyen@ecy.wa.gov.
To request language services (interpreting/translation), contact Ecology by phone at 425-393-5679 or email nancy.lui@ecy.wa.gov or visit https://ecology.wa.gov/About-us/Accessibility-equity/Language-services. For Relay Service or TTY call 711 or 877-833-6341.
Documents 92
Legal 4
Document Title | Document Date | Document Type |
Maralco Agreed Order - Final January 2024 | 1/17/2024 | Agreed Order |
Maralco PLP Determination Letter | 9/14/2023 | Final Potentially Liable Person Status Letter |
Maralco - Lien - Proposed Settlement Agreement | 6/19/1989 | Lien related document |
Maralco - Notice of Claim of Lien | 8/9/1988 | Lien related document |
Map 1
Document Title | Document Date | Document Type |
Maralco - Record of Survey | 4/9/1991 | Map |
Outreach Information 14
State Environmental Policy Act 3
Document Title | Document Date | Document Type |
Maralco - NW3339 Ecology Comment Letter for SEPA | 4/7/2023 | SEPA Documents |
Maralco - NW3339 Ecology Comment Letter for SEPA | 7/20/2022 | SEPA Documents |
Maralco - NW3339 SEPA Checklist | 4/18/2022 | SEPA Documents |
Technical Reports 63
Document Title | Document Date | Document Type |
Maralco - Letter Re: Change of Ecology Project Coordinator | 9/5/2025 | Site Specific Administrative Document - Other (Administrative Correspondence) |
Maralco 2Q25 Progress Report (Apr-Jun 2025) | 7/10/2025 | Progress Report |
Maralco 1Q25 Progress Report (Jan-Mar2025) | 4/10/2025 | Progress Report |
Maralco - Ecology Approval Letter for Supplemental Remedial Investigation Work Plan | 2/3/2025 | Site Specific Administrative Document - Other (Administrative Correspondence) |
Maralco - Supplemental Remedial Investigation Work Plan | 1/27/2025 | Remedial Investigation Work Plan |
Maralco 4Q24 Progress Report (Oct-Dec 2024) | 1/10/2025 | Progress Report |
Maralco - Final Interim Action Work Plan, Phase 2 Removal Action | 12/30/2024 | Interim Action Plans and Reports |
Maralco - Ecology Approval Letter for Interim Action Work Plan, Phase 2 Removal Action | 12/30/2024 | Site Specific Administrative Document - Other (Administrative Correspondence) |
Maralco 3Q24 Progress Report (Jul-Sep 2024) | 10/18/2024 | Progress Report |
Maralco - SHARP Report | 7/24/2024 | Site Hazard Assessment and Ranking Process Report |
Maralco 2Q24 Progress Report (Apr - June 2024) | 7/10/2024 | Progress Report |
Maralco Ecology Key Comments on IAWP - Letter | 6/6/2024 | Site Specific Administrative Document - Other (Administrative Correspondence) |
Maralco Ecology Key Comments on IAWP - Comment Matrix | 6/6/2024 | Site Specific Administrative Document - Other (Administrative Correspondence) |
Maralco 1Q24 Progress Report (Jan-Mar 2024) | 4/10/2024 | Progress Report |
Maralco Interim Action Report | 2/6/2024 | Interim Action Plans and Reports |
Maralco - NW3339 Revised Interim Action Work Plan - Text, Tables, Figures | 7/25/2023 | Interim Action Plans and Reports |
Maralco - NW3339 Revised Interim Action Work Plan, Appendices | 7/24/2023 | Interim Action Plans and Reports |
Maralco - NW3339 Remedial Investigation Work Plan Addendum | 6/23/2023 | Site Specific Technical Document - Other |
Maralco - NW3339 Remedial Investigation Work Plan | 3/16/2022 | Remedial Investigation Work Plan |
Maralco - NW3339 Limited Phase II Environmental Site Assessment Report | 3/21/2017 | Site Specific Technical Document - Other |
Maralco - Phase I Environmental Site Assessment Report | 7/20/2015 | Site Specific Technical Document - Other |
Maralco - Cost Report Package | 8/31/2010 | Site Specific Technical Document - Other |
Maralco - Waste Characterization Project | 8/30/2007 | Site Specific Technical Document - Other |
Maralco - Acute Oral Rat Toxicity Test | 9/8/2006 | Site Specific Technical Document - Other |
Maralco - Addendum, Sampling and Analysis Plan | 6/8/2006 | Sampling and Analysis Plan |
Maralco - Acute Oral Rat Toxicity Test | 3/20/2006 | Site Specific Technical Document - Other |
Maralco - Revised Proposed Closure Strategy | 3/20/2006 | Site Specific Technical Document - Other |
Maralco - Dangerous Waste Characterization | 2/14/2006 | Site Specific Technical Document - Other |
Maralco - Summary Data Quality Review | 11/28/2005 | Site Specific Technical Document - Other |
Maralco - Metals Analysis | 11/17/2005 | Site Specific Technical Document - Other |
Maralco - Sampling and Analysis Plan/Quality Assurance Project Plan | 9/9/2005 | Sampling and Analysis Plan |
Maralco - Complete Summary Format Market Value Appraisal | 4/20/2005 | Site Specific Technical Document - Other |
Maralco - Draft Cleanup Action Plan | 11/12/2004 | Cleanup Action Plan |
Maralco - Proposed Supplemental Waste Characterization Sampling | 10/13/2004 | Site Specific Technical Document - Other |
Maralco - Remedial Investigation/Feasibility Study | 5/16/2003 | Remedial Investigation / Feasibility Study Report |
Maralco - Remedial Investigation/Feasibility Study, Large Figures | 5/16/2003 | Remedial Investigation / Feasibility Study Report |
Maralco - Revised Wetland Delineations | 4/25/2003 | Site Specific Technical Document - Other |
Maralco - Revised Wetland Delineations, Sheet 1 of 1 | 4/22/2003 | Site Specific Technical Document - Other |
Maralco - Black Dross Pile Characterization | 8/31/2000 | Site Specific Technical Document - Other |
Maralco - Initial Request for Prospective Purchaser Agreement | 6/20/2000 | Site Specific Technical Document - Other |
Maralco - Analytical Test Results | 8/15/1996 | Site Specific Technical Document - Other |
Maralco - Underground Storage Tank Decommissioning | 7/31/1995 | Site Specific Technical Document - Other |
Maralco - Characterization of Drummed Wastes | 6/22/1995 | Site Specific Technical Document - Other |
Maralco - Task 2 Workplan, Implementation of Selected Cleanup Actions | 6/6/1995 | Site Specific Technical Document - Other |
Maralco - Task 1, Review of Options for Remediation | 5/3/1995 | Remedial Investigation / Feasibility Study Report |
Maralco - Notes for 55% Completion Meeting | 12/12/1994 | Site Specific Technical Document - Other |
Maralco - Phase II Environmental Site Assessment | 8/5/1994 | Site Specific Technical Document - Other |
Maralco - Air Photos | 6/1/1993 | Site Specific Technical Document - Other |
Maralco - Recycled Aluminum Metals Co. Salt Cake Stockpile Sampling Plan | 5/13/1993 | Site Specific Technical Document - Other |
Maralco - Construction As-Built Report | 12/3/1991 | Remedial Action/As-Built Report |
Maralco - Work Plan for Ongoing RI/FS Activities | 6/5/1991 | Remedial Investigation Work Plan |
Maralco - Phase 1 Feasibility Study Report | 3/1/1991 | Feasibility Study |
Maralco - Phase I Remedial Investigation Report | 2/1/1991 | Remedial Investigation Report |
Maralco - International Aluminum Inc. Health and Safety Plan | 8/27/1990 | Health and Safety Plan |
Maralco - MK Environmental Services Health and Safety Plan | 8/3/1990 | Health and Safety Plan |
Maralco - Remedial Investigation Data and Analysis | 5/22/1990 | Site Specific Technical Document - Other |
Maralco - Phase II Environmental Assessment | 4/30/1990 | Site Specific Technical Document - Other |
Maralco - Revised Remedial Investigation/Feasibility Study Work Plan | 3/19/1990 | Remedial Investigation Work Plan |
Maralco - International Aluminum Inc. Prospectus & Feasibility Study | 8/4/1989 | Site Specific Technical Document - Other |
Maralco - Technical Assistance Team Site Assessment Report | 10/1/1987 | Site Specific Technical Document - Other |
Maralco - Verifications and Requirements | 8/4/1986 | Site Specific Technical Document - Other |
Maralco - Impact of Western Processing on Water Quality in Mill Creek | 1/1/1985 | Site Specific Technical Document - Other |
Maralco - Western Processing Final Hydrogeologic Assessment | 10/16/1984 | Site Specific Technical Document - Other |
Voluntary Cleanup Program 7
Document Title | Document Date | Document Type |
Maralco NW3339 - VCP Termination Letter | 1/18/2024 | VCP Administrative Document |
Maralco - NW3339 Ecology Technical Assistance on IAWP July 31 2023 | 7/31/2023 | VCP Technical Assistance |
Maralco - NW3339 VCP Opinion Letter | 8/24/2022 | VCP Opinion on Site Cleanup – Other |
Maralco - NW3339 VCP Application Acceptance | 6/16/2022 | VCP Administrative Document |
Maralco - Termination of VCP Agreement | 3/6/2013 | VCP Administrative Document |
Maralco - Request for Information on VCP Project | 1/24/2013 | VCP Administrative Document |
Maralco - Request for information on status of VCP | 7/23/2012 | VCP Administrative Document |
Places to see print documents
-
King County Library - Kent Library212 2nd AVE NKent, 98032This location may only have print documents available during open comment periods.
Contaminants 3
Contaminant Type | Soil |
Groundwater |
Surface Water |
Air |
Sediment |
Bedrock |
---|---|---|---|---|---|---|
Metals - Metals - Other | C | C | S | |||
Other Contaminant - Conventional Contaminants, Inorganic | C | S | ||||
Non-Halogenated Organics - Petroleum-Diesel | C | C |
- S
- Suspected
- C
- Confirmed Above Cleanup Levels
- B
- Below Cleanup Levels
- RA
- Remediated-Above
- RB
- Remediated-Below
- R
- Remediated