Gas Works Park
Status: Sediment Unit Engineering Design Underway
Last Updated: October 2026
Back in July 2023, Ecology approved the cleanup action plan at Gas Works Park. The plan includes digging up and covering contaminated soil along the shoreline, treating polluted groundwater near the shoreline, dredging and capping dirty sediment in the water, doing ongoing monitoring, and putting rules in place for how the area can be used in the future. This cleanup plan is part of a legal agreement (called a consent decree) between Ecology, the City of Seattle (City), and Puget Sound Energy (PSE). That agreement became final in January 2024. It requires the City and PSE to design and build the cleanup as described in the plan.
In early 2024, Ecology approved a work plan to gather more information to better define where contamination is and to help design the cleanup. From March to October 2024, investigations were carried out on land, along the shoreline, and in the water. In March 2025, the U.S. Army Corps of Engineers approved a permit giving permission for sampling work in the water, which wrapped up at the end of 2025. Ecology is still reviewing all the data collected during that phase.
In August 2026, Ecology approved a separate work plan to clean up groundwater in one specific area of the site (called GWMA‑1).That cleanup is expected to start in late 2026 and continue through 2028.
2026 through 2028: Clean up groundwater in GWMA-1.
2026 through 2029: Engineers will keep working on the design and permitting for the cleanup work that will happen in the water. This includes doing more studies to better understand the contamination and finalize how the cleanup should be built.
2029/2030: Begin construction of the in-water cleanup work.
Site Units And Remaining Contaminated Areas
Sediment throughout the Sediment Unit is contaminated.
Contaminants present are from former upland industrial operations and include polycyclic aromatic hydrocarbons, arsenic, nickel, carbazole and dibenzofuran. Additional contaminants associated with other sources in Lake Union are also present in sediment.
General Cleanup Process
What Happens Next?
- June 20 - July 20, 2023: Public comment period
- June 28, 2023: Online public meeting (Download presentation PDF)
- Fall 2023: Public comments addressed, and cleanup action plan finalized
- 2023 to 2027: Engineering design and permitting, including additional investigations and evaluations to refine the cleanup action and enable detailed design work
- 2027: Begin construction
Public Participation
This plan includes information for the public regarding opportunities to get involved in the Site cleanup process. The outreach activities and mechanisms presented reflect Ecology’s current plans for keeping the public informed and for receiving information and comments from the public.
Site Information
Formerly territory occupied by three indigenous communities (the Duwamish, Hachooabsh, and Shilsholes), the area surrounding the northern portion of Lake Union was settled by non-natives in the mid- to late 1800s. In 1907, construction of a manufactured gas plant was completed on the upland area of the Gas Works Park site to supply fuel for the growing population of Seattle. The plant operated until 1956. Other industries (e.g., tar refining, bulk fuel storage, shipbuilding) also historically operated in the upland area. These past industrial activities resulted in contamination of soil, groundwater and sediment.
Contamination in the upland area has been largely addressed through multiple cleanup actions completed between 1971 and 2020.
Location
The Gas Works Park site is located at 2101 N Northlake Way, Seattle, Washington on Lake Union. It consists of approximately 21 upland acres (Upland Unit) and approximately 56 in-water acres (Sediment Unit).
The City of Seattle owns the majority of the Upland Unit and the State of Washington owns the majority of the Sediment Unit.
Pictures
Site use restrictions called institutional controls are in effect
Institutional controls can be fences, signs, or restrictions on how the property is used. For instance, an institutional control may prohibit installing drinking water wells or disturbing a protective cap that isolates contamination. These restrictions keep the contamination contained and keep people from being exposed to the contamination. The controls are usually listed in environmental covenants recorded with the county.
Periodic reviews are required when institutional controls are required at a site. Ecology conducts reviews to make sure the controls remain effective and the cleanup still protects human health and the environment. We conduct periodic reviews about every five years.
Institutional Controls 2
Environmental Covenant
Restrictions/Requirements
- Ongoing Maintenance of Remedy
- Prohibit Removal or Alteration of Existing Buildings
- Prohibit Soil Disturbance
- Restrict All Ground Water Extraction/Well Installation
Restricted Media
- Groundwater
- Soil
Environmental Covenant
Restrictions/Requirements
- Ongoing Maintenance of Remedy
- Prohibit Removal or Alteration of Existing Buildings
- Prohibit Soil Disturbance
- Restrict All Ground Water Extraction/Well Installation
Restricted Media
- Groundwater
- Soil
Documents 127
Legal 18
Outreach Information 29
State Environmental Policy Act 7
| Document Title | Document Date | Document Type |
| Gas Works Park Sediment Unit - SEPA Determination and Checklist - June 2023 | 6/20/2023 | SEPA Documents |
| SEPA Determination of Non-Significance - Addendum | 9/11/2017 | SEPA Documents |
| Play Area SEPA Figures | 2/27/2017 | SEPA Documents |
| SEPA Determination of Nonsignificance | 2/24/2017 | SEPA Documents |
| Play Area SEPA Checklist Updated | 2/22/2017 | SEPA Documents |
| Gas Works Park - SEPA Checklist (June 2012) | 6/15/2012 | SEPA Documents |
| Gas Works Park - Determination of Non-Significance (June 2012) | 6/15/2012 | SEPA Documents |
Technical Reports 73
Places to see print documents
-
Northwest Regional Office15700 Dayton Ave NShoreline, 98133Please schedule an appointment to view print documents at this location.
-
Fremont Public Library731 N 35th StreetSeattle, 98103This location may only have print documents available during open comment periods.
Contaminants 4
| Contaminant Type | Soil |
Groundwater |
Surface Water |
Air |
Sediment |
Bedrock |
|---|---|---|---|---|---|---|
| Halogenated Organics - Halogenated Organics | C | |||||
| Metals - Metals Priority Pollutants | S | |||||
| Non-Halogenated Organics - Petroleum Products-Unspecified | C | C | ||||
| Non-Halogenated Organics - Polycyclic Aromatic Hydrocarbons | C | C |
- S
- Suspected
- C
- Confirmed Above Cleanup Levels
- B
- Below Cleanup Levels
- RA
- Remediated-Above
- RB
- Remediated-Below
- R
- Remediated